Briefing for a Successful STEM Building

image
Equals Consulting

By James Sheppard

October 2017

Many institutions are seeking to expand their STEM capacity and teaching capability to meet national, regional and local policy ambitions, attract investment, increase student numbers and enhance skills for the workplace.

For some, this will link to readiness for the new T-Levels, for others it will also be about expanding apprenticeships in these sectors, while for some it may also link with a bid for one of the new Institutes of Technology.

 

New Build or Retro-fit

Some academic STEM programmes can be accommodated in existing laboratories and teaching space. But when STEM teaching seeks to really exploit new opportunities offered by evolving technology, this leads to a need for new types of space and new relationships between spaces. Whichever path is chosen, the works will need to be designed, procured and constructed, and the key to this is a good client brief.

 

What should a STEM building do?

There is no ‘cookie cutter’ pattern; the specific requirements will be generated by curriculum needs, but will need to:

  • — Align with the vision and strategic aims of the institution
  • — Provide accommodation to meet current and future teaching, training and research needs of different types of provision
  • — Promote the success of students on their course and in future employment
  • — Have the capability to cater for substantial technology/equipment and for future upgrades
  • — Be deliverable in terms of cost, time and quality
  • — Be sustainable to meet both environmental needs and constrain running costs.

Briefing

Briefing for a STEM building can pose a challenge; particularly if it is to offer ‘leading edge’ facilities. Many academic and technical staff will know more about the teaching and equipment requirements than the designers specifying the project. Conversely it may not be possible to accurately predict future requirements, due either to uncertainty over evolving technology, or to late contracting of industry partners. Either way, to ensure success, care needs to be taken to communicate this well.

 

Flexibility is not the Answer

The word ‘flexibility’ can lead to impractical, expensive and often rarely used solutions, such as moveable walls or the over provision of power and data. Designers and engineers respond better to constraints. Instead try to focus on ADAPTABILITY. Accept that requirements evolve over time and alterations will be inevitable, and brief on an adaptable building to meet the immediate need without being over specific and creating obstacles to make future adaptation costly and impractical.

 

Paradigm Site Visits

Site visits as a team to similar facilities are invaluable, whether STEM teaching facilities or similar spaces within industry; they can:

  • — Help build knowledge of new processes
  • — Reduce mistakes by lessons learned in use
  • — Convey real life examples to designers
  • — Foster relationships with business
  • — Help reach consensus of quality levels
  • — Understand adjacencies.

 

Large Open Plan Spaces

Not to be confused with ‘clear span’, as to a designer this means long span beams and enhanced foundations which increase cost. Instead, ask designers to investigate a standardized column grid that can easily allow subdivision into workable spaces of all sizes for all potential uses, whether workshops, teaching spaces or seminar rooms.

Services

Encourage engineers to think about allowing future adaptation by investigating the following:

  • — Ceiling mounted main services spines on a standardized grid; to be connected when adapting in future.
  • — Provide as much in-built capacity for expansion as possible, carry out cost studies to consider whether it is worth investing at the time or allowing space to increase later.
  • — Local Exhaust Ventilation – LEV can be onerous in terms of Health & Safety and also sterilize areas of the building due to restrictions imposed by exhaust locations.
  • — Information Technology evolution speed – be wary of purchasing or specifying too widely.
  • — Heating and cooling will respond to usage, so make sure that the provision at day one is judged on what is actually required, with the provision to possibly upgrade later.

 

Ground Floor Use

Are vehicles or large pieces of equipment likely to be required? A large door or shutter with level access allows this to happen easily. Goods lifts can be very expensive to install and maintain and should be judged on potential usage. Floor loadings should be carefully considered and optimised to avoid cost.

Building as Teaching Aid

Be aware that the look, feel and structure of the building can be used to aid students understanding of technical delivery, especially with exposed services and structure and also the finished BIM model.

What would Industry do?

Take soundings from industry on how they are approaching the spaces that they use. Not only will it allow lessons to be learned but it will foster links that might help in terms of student placements and equipment use or loan. For Institute of Technology projects, such links will be essential to secure a bid.

 

Use the Right Consultants, then Communicate, Question and Measure

This is an area which benefits particularly from having building consultants with experience and who show a willingness to listen and respond to a client brief. Give the designers the leeway to be creative as they have the skills to provide surprising results. Each building project will be bespoke, and these suggestions are only prompts to help you as client communicate your brief to the designers as successfully as possible; but make sure that the brief is used to measure each design stage response against the core briefing principles.

This will ensure that as far as possible the STEM building that you create provides the best value in the short term and also over the life of the asset; supporting academic process in the best way possible.

 

Project Example

Oaklands College
Engineering Resource Centre

Value: £9million
Client: Oaklands College

  • — Open plan spaces
  • — Adaptable grid
  • — Building as a teaching aid
  • — High floor loadings and vehicle sized entry door
  • — Ceiling mounted services